CGR Saint-Yorre: from 70% to 85% OEE in two weeks
After visiting the plant, one of CGR Saint-Yorre’s largest customers complained in writing about the lack of dashboards, real production monitoring and OEE management on the shop floor, along with declining performance. The site, which specialises in cold forming tubes and wire for the automotive industry, then rolled out Astn’go. About two weeks later, its OEE had risen from 70% to 85%.
70% → 85%
OEE after about two weeks
“2 minutes”
to install the IIoT box, according to Calixte Mengoua: “all you need is a screwdriver”
3 weeks
to have the solution up and running on the shop floor
3 seconds
to see where production stands, on the tablets and PCs already on the shop floor
A warning from their largest customer
The Saint-Yorre site is part of the CGR group, France’s leading spring manufacturer: over €240 million in revenue and 23 plants in 11 countries. Calixte Mengoua, the site’s Lean & Kaizen coach, remembers how it started:
« It all started when we received an email from one of our largest customers with the subject line “Critical situation at CGR”. The customer rightly criticised us for having no dashboards, no real production monitoring and no effective OEE management on our shop floor. »
Calixte MENGOUA, Lean & Kaizen coach, CGR Saint-Yorre
To respond quickly, the plant started with paper tracking sheets, filled in every hour by the operators. The case study explains what this method cost the teams, and how they moved to real-time monitoring in three weeks.

Calixte Mengoua
Lean & Kaizen coach, CGR Saint-Yorre
“ HE SAYS IT BETTER THAN WE DO
All you need is a screwdriver. It’s the only thing I’ve ever had maintenance install without them grumbling. And that says a lot!
What the teams say
« We got started on our own at our production site and everything works. Within 3 weeks, the solution was up and running on our shop floor. »
Philippe LANOIZELE, Lean Manager, CGR Saint-Yorre
« In three seconds, we know where production stands. And in three clicks, I can produce all my summaries and analyses. »
Calixte MENGOUA, Lean & Kaizen coach, CGR Saint-Yorre
« All the actions we put in place with Astn’go took our OEE from 70% to 85% in just two weeks or so. »
Calixte MENGOUA, Lean & Kaizen coach, CGR Saint-Yorre

In the case study, find out:
- the email that started it all, and how the plant responded in under three weeks
- what paper tracking really cost operators and managers
- how the IIoT box was installed without an IT project or new hardware
- what changed day to day for managers and operators
- the full project fact sheet
3 pages to share with your management or your teams.